How do you shingle your screened in porch in seven hours? Hire us. We've needed to do this for a while but it didn't leak so what was the rush? Unfortunately for us our hand was forced and we needed to get it done. The weather hasn't exactly been cooperating so when we finally got a nice day we went for it. The work was started at roughly 4:30pm and work completed at about 12:00am. Everyone chipped in to get this done and it doesn't look half bad.
We had the roof cleared of all the old debris at about 5:30pm.
I'm going to guess this was about 7:30pm or so, we had all the new tar paper in place.
The ground crew measuring and cutting everything we needed to make the install go smoothly.
At about 9:30 SamCo was showing me how to properly apply bug spray. Oh and we had fourish rows of shingles down.
Thanks to Minion for this picture at 12:10am or so. I couldn't have climbed the tower if my life depended on it.